TransPAC Network Operations Report
02/11/2013 - 02/17/2013

TransPAC Network Operations Center
at Indiana University

New Connections

None


Upgrades

None


New Services

None


Unscheduled Outages Summary

Ticket Number Customer Impact Network Impact Title Outage Type Start Time (UTC) End Time (UTC)


None during this report period

Scheduled Maintenances Summary

Ticket Number Customer Impact Network Impact Title Maintenance Type Start Time (UTC) End Time (UTC)

None during this report period

Downtime and Availability



TransPAC Core NodesDown TimeReporting Period Availability52 Week Availability
TransPAC MX480 - LA0 hr 0 min100.00000%100.00000%
6410 Ethernet Switch0 hr 0 min100.00000%99.99943%
3410 Ethernet Switch0 hr 0 min100.00000%100.00000%
OOB Router0 hr 0 min100.00000%100.00000%

Aggregate TransPAC Core Nodes0 hr 0 min100.00000%99.99986%

TransPAC Backbone CircuitsDown TimeReporting Period Availability52 Week Availability
TransPAC LOSA-JGN2 LOSA 10GigE0 hr 0 min100.00000%99.99943%
TransPAC LOSA-Pacific Wave LOSA 10GigE0 hr 0 min100.00000%99.99943%
TransPAC TOKY-TransPAC2 LOSA0 hr 0 min100.00000%99.88174%

Aggregate All TransPAC Backbone Circuits0 hr 0 min100.00000%99.96020%




Upcoming Scheduled Maintenances

Ticket No.:1326:62
Subject:TransPAC Core Node LOSA Maintenance
Affected:TransPAC2 LOSA-JGN2 LOSA 10GigE
TransPAC LOSA-Pacific Wave LOSA 10GigE
Start Time:Wednesday, February 27, 2013, 1:00 AM (0100) UTC
End Time:Wednesday, February 27, 2013, 2:00 AM (0200) UTC
Description: The above circuits will be unavailable while TransPAC Engineering performs maintenance to replace hardware. An outage of up to an hour is expected and the entire window is reserved. Traffic will continue to pass via TP-LOSA-TOKY-10GE-1